马上注册,结交更多好友,享用更多功能,让你轻松玩转社区。
您需要 登录 才可以下载或查看,没有帐号?FreeOZ用户注册
x
一个印度申请人,打通了DIAC电话,和接线员聊了半小时
对方答复如下
1.
Q: 我收到了318邮件,现在还剩6天道618,我还没分CO;到618我会分到CO吗?
A: 的确,目前不是所有的318收件人都分到CO。但DIAC在尽最大努力尽快让这些人分到CO。即使拖期也不会托超过几周(原话是a couple of weeks)
2.
Q: 是否可以查查我的TRN号的情况?如果超出618,什么时候会给我分CO?
A: 不可以。无法确认时间表。
3.
A:此外,CO在分到你的case后,会花多达6周时间去评估(assess)你的case。因此存在可能性,CO在618的时候已经开始看你的case,但是还没做完评估,所以没联系你。
如果收到318邮件的申请人,在618之后的6周后,还没有得到CO的联系,可以联系DIAC,DIAC会立刻审阅你的case(原话是immediately look into your case)
(donghao43注释:言外之意是618的deadline拖到7月29是合理的,7月29=6月18+6周)
===========================附英文原文========================================
Called to DIAC
--------------------------------------------------------------------------------
I just called to DIAC 50 minutes back... was lucky that someone picked up the call within 30 minutes.
-------------------
I spoke to her about my case that I have recieved the 18 marh email and as per its directive, I have uploaded all the required documents and my aplpication is up-to-date for processing. But yet i am to recieve a CO and only 6 days have left.
She responded that they have not allocated COs to all people to whom they have sent 18 march email. They are trying to poccess all 18 march people at the earliest, but there is no conformative timelines as when you will be contacted.
So I asked is there a surety that I will get a CO by 18 June as per 18 March email. She said NO
But she said that they are trying to allocate COs at their best and there should not be any huge delay other than couple of weeks.
She also mentioned that once a CO pics your case file, it might take him/her 6 weeks to initially assess your case. She also said that their might be a possibility that some CO might already be looking into my case and initial assessment might have started.
So for me she said that for worst case could be that you (18 march applicants) will get a definite outcome by July end. If you do not get contacted by a CO till then, please do call us and we will immediately look into your case.
-------------------
Now in this complete conversation i tried many times to give her my TRN or File number, but she refused to take it saying as you have already recieved 18 march email, you will definitely get a CO soon. She mentioned that they are trying their level best to allocate COs at the earliest to meet the timeline....
After speaking to her, atleast i feel positive that due to some reasons, they might not be able to meet the timeline of 18 march for everyone, but it will not be delayed by more than couple of weeks...
So I am now hoping to wait till june end and see whats the update... I am hoping I should get a CO by June end!!!:jug gle:
-Ninja-
__________________
-----------------------------------------------------------------------
175 Applied: 22-Feb-2011 | Medical: Mar-2011 | PCC: Mar-2011 | CO Allocation: xx-2011
[ 本帖最后由 donghao43 于 9-6-2011 17:33 编辑 ] |
评分
-
查看全部评分
|